The Facility Condition Index (FCI) rating is a measurement of the condition of a school building. It does not reflect on the safety of the building.

The health and safety of students, staff and community members are our top priority when planning school repairs. Our Facility Services staff works year-round to ensure our schools are safe regardless of their FCI rating.

Almost half of TDSB school buildings were built more than 60 years ago. Older schools often have a higher FCI rating as some building components such as walls, lights, floors and ventilation systems may require major repairs or replacement.


F.C.I.
61.30 %

Learn More

Learn more about the Renewal Needs Backlog and the Facility Condition Index, both of which include related Frequently Asked Questions.

Renewal Needs Backlog

The Toronto District School Board’s Renewal Needs Backlog (RNB) list identifies approximately 20,400 different repairs needed in our schools. The total value of those repairs was $4.2 billion as of March 2023.

For the 2022-2023 school year, the TDSB  received $292 million in provincial funding. These funds will be used to replace/repair building components identified during the Ministry’s school inspections, helping reduce the FCI of school buildings.

It is important to understand that these repairs do not represent a health or safety concern. Safety is a top priority for us at the TDSB and our maintenance plans are always focused on providing safe places for our students and staff. In order to do that, we fix the most critical problems related to health and safety first. Also, while components in a school building may be past their life expectancy (e.g. water boiler), they are in good condition and meet all required safety codes.

Legend

Urgent Building systems that are in critical condition and have surpassed their useful service life. These systems are very important to the operation of the building (e.g. boilers, other heat generating systems, fire alarm, sprinkler system, standpipe system, public address system, roofing, etc.). Although there is no specific timeframe to repair/replace these systems, it is recommended to do it as soon as funding becomes available.
High Building systems that are in critical or poor condition and their importance to the operation of the building is less than those classified as “urgent” (e.g. brick work, exterior doors, exterior windows, rooftop units, etc.). There is no specific timeframe to repair/replace these systems; however, repair/replacement is recommended as soon as funding becomes available.
Medium Building systems that are in fair condition with low importance to the operation of the building (e.g. floor finishes, washroom partitions, millwork, etc.).
Low Building systems that are in fair or good condition with very low importance to the operation of the building (e.g. wall partitions, interior wall finishes, interior doors, fences, etc.).
Brief DescriptionPriority
A101004 Standard Foundations Repairs - Parging repairs RenewalUrgent
Auxiliary Equipment - Expansion Tanks RenewalUrgent
Auxiliary Equipment - Stacks & Breaching RenewalUrgent
Distribution Systems - Heated Water Distribution Systems - Piping System RenewalUrgent
Hot Water Boilers - Boiler #1 & #2 RenewalUrgent
Interior Stair Construction - Original Building & Additions 1, 2 and 3 RenewalUrgent
Main Switchboards - Main Disconnect RenewalUrgent
Roof Coverings - Section A,A1,A2,D1,D2 RenewalUrgent
Site Civil/Mechanical Utilities RenewalUrgent
B201014 Exterior Walls - Masonry Re-pointing RenewalHigh
C302004 Floor Finishes - Vinyl Tile RenewalHigh
Ceiling Finishes - Acoustic Tile Ceiling - Original Building & Additions 1, 2 and 3 RenewalHigh
Controls and Instrumentation - Electronic/BAS RenewalHigh
Distribution Systems - Exhaust Systems - Axial RenewalHigh
Distribution Systems - Exhaust Systems - Centrifugal RenewalHigh
Domestic Water Distribution - Pipes and Fittings RenewalHigh
Energy Supply System - Natural Gas - Piping RenewalHigh
Exterior Doors - Hardware RenewalHigh
Exterior Doors - Original Building & Additions 1, 2 and 3 RenewalHigh
Fin Tube Radiation Units - Perimeter Heating RenewalHigh
Fittings - Millwork - Original Building & Additions 1, 2 and 3 RenewalHigh
Floor Finishes - Hardwood - Gymnasium RenewalHigh
Interior Doors - Hardware - Original Building & Additions 1, 2 and 3 RenewalHigh
Interior Doors - Original Building & Additions 1, 2 and 3 RenewalHigh
Lighting Equipment - Exterior - Wall RenewalHigh
Lighting and Branch Wiring - Branch Wiring - Cabling, Raceways & Bus Ducts RenewalHigh
Lighting and Branch Wiring - Exterior - Pole RenewalHigh
Parking Lots - Asphalt - Site RenewalHigh
Pedestrian Paving - Asphalt - Site RenewalHigh
Playing Fields - Paved RenewalHigh
Playing Fields - Unpaved - Site RenewalHigh
Plumbing Fixtures - Bradley Basins RenewalHigh
Plumbing Fixtures - Lavatories RenewalHigh
Plumbing Fixtures - Water Closets RenewalHigh
Rain Water Drainage RenewalHigh
Sanitary Waste - Piping RenewalHigh
Structural Frame - Original Building & Additions 1, 2 and 3 RenewalHigh
Terminal and Package Units - Unit Ventilators RenewalHigh
Wall Finishes - Painted - Original Building & Additions 1, 2 and 3- Older RenewalHigh
B2020 Exterior Windows RenewalMedium
C1010 Partitions - Localized deficiencies RenewalMedium
Domestic Water Distribution - Electric Hot Water Heater RenewalMedium
Domestic Water Distribution - Drinking Fountains and Coolers RenewalLow