Facility Condition Index

2024 -2025

The Facility Condition Index (FCI) rating is a measurement of the condition of a school building. It does not reflect on the safety of the building.

The health and safety of students, staff and community members are our top priority when planning school repairs. Our Facility Services staff works year-round to ensure our schools are safe regardless of their FCI rating.

Almost half of TDSB school buildings were built more than 60 years ago. Older schools often have a higher FCI rating as some building components such as walls, lights, floors and ventilation systems may require major repairs or replacement.


F.C.I.
73.07 %

Renewal Needs Backlog

The Toronto District School Board’s Renewal Needs Backlog (RNB) list identifies approximately 25,600 different repairs needed in our schools. The total value of those repairs was $4.45 billion as of January 2025.

For the 2022-2023 school year, the TDSB  received $292 million in provincial funding. These funds will be used to replace/repair building components identified during the Ministry’s school inspections, helping reduce the FCI of school buildings.

It is important to understand that these repairs do not represent a health or safety concern. Safety is a top priority for us at the TDSB and our maintenance plans are always focused on providing safe places for our students and staff. In order to do that, we fix the most critical problems related to health and safety first. Also, while components in a school building may be past their life expectancy (e.g. water boiler), they are in good condition and meet all required safety codes.

Legend

Urgent Building systems that are in critical condition and have surpassed their useful service life. These systems are very important to the operation of the building (e.g. boilers, other heat generating systems, fire alarm, sprinkler system, standpipe system, public address system, roofing, etc.). Although there is no specific timeframe to repair/replace these systems, it is recommended to do it as soon as funding becomes available.
High Building systems that are in critical or poor condition and their importance to the operation of the building is less than those classified as “urgent” (e.g. brick work, exterior doors, exterior windows, rooftop units, etc.). There is no specific timeframe to repair/replace these systems; however, repair/replacement is recommended as soon as funding becomes available.
Medium Building systems that are in fair condition with low importance to the operation of the building (e.g. floor finishes, washroom partitions, millwork, etc.).
Low Building systems that are in fair or good condition with very low importance to the operation of the building (e.g. wall partitions, interior wall finishes, interior doors, fences, etc.).
Brief DescriptionPriority
Auxiliary Equipment - Expansion Tanks RenewalUrgent
Auxiliary Equipment - HVAC Pumps RenewalUrgent
Auxiliary Equipment - Stacks & Breaching - Boiler #2 RenewalUrgent
Hot Water Boilers - Boiler #2 RenewalUrgent
Roof Coverings - Section A,A4 RenewalUrgent
Standard Foundations Repairs - Parging repairs RenewalUrgent
Air Handling Units - AHU #3 and #4 RenewalHigh
Auxiliary Equipment - Chemical Feed System RenewalHigh
Auxiliary Equipment - Heat Exchanger - Shell & Tube RenewalHigh
Branch Wiring - Original RenewalHigh
C103001 Fittings - Washroom Partitions - Water Closet RenewalHigh
Ceiling Finishes - Suspended Acoustic Ceilings RenewalHigh
Cooling Generating Systems - Condenser #1 and #2 RenewalHigh
Distribution Systems - Exhaust Systems - Axial RenewalHigh
Domestic Water Distribution - Natural Gas DWH RenewalHigh
Domestic Water Distribution - Plumbing Piping System - Original Building RenewalHigh
Exterior Doors - Hardware RenewalHigh
Exterior Doors - RenewalHigh
Exterior Walls - Masonry Re-pointing RenewalHigh
Fin Tube Radiation Units - Original RenewalHigh
Floor Finishes - Carpet RenewalHigh
Floor Finishes - Hardwood - Parquet Flooring RenewalHigh
Lighting Equipment - Exterior Lighting RenewalHigh
Pedestrian Paving - Concrete & Asphalt Paved RenewalHigh
Plumbing Fixtures - Lavatories RenewalHigh
Plumbing Fixtures - Urinals RenewalHigh
Plumbing Fixtures - Water Closets RenewalHigh
Plumbing Fixtures - Water Fountains RenewalHigh
Retaining Walls - Rail Ties RenewalHigh
Air Distribution, Heating & Cooling - Ductwork RenewalMedium
C102007 Interior Doors - Hardware RenewalMedium
Controls & Instrumentation - BAS RenewalMedium
Electrical Service and Distribution - Panel (600, 220, 120 V) RenewalMedium
Elevators & Lifts - WCA RenewalMedium
Fencing & Gates - Galvanized Fencing RenewalMedium
Floor Finishes - Ceramic Floors RenewalMedium
Floor Finishes - Sheet Vinyl RenewalMedium
Interior Doors - Older Wood and Hollow Metal RenewalMedium
Roof Coverings - Section A2 RenewalMedium
Signage - All RenewalMedium
Site Civil/Mechanical Utilities RenewalMedium
Wall Finishes - Paint Wallcovering - 60% RenewalMedium
Ceiling Finishes - Painted Gym Ceiling Structures RenewalLow
Controls & Instrumentation - EMS RenewalLow
Domestic Water Distribution - Backflow Preventer 1 RenewalLow
Domestic Water Distribution - Backflow Preventer 2 RenewalLow
Fittings - All - Chalk and Tack Boards, Kitchen Equip and Signage RenewalLow
Fittings - Washroom Accessories RenewalLow
Fittings - Window Coverings - Blinds and Curtains RenewalLow
Landscaping RenewalLow

Learn More

Learn more about the Renewal Needs Backlog and the Facility Condition Index, both of which include related Frequently Asked Questions.