Toronto District School Board
Skip to main content

Tom Longboat Junior Public School

Facility Condition Index

2022 -2023

The Facility Condition Index (FCI) rating is a measurement of the condition of a school building. It does not reflect on the safety of the building.

The health and safety of students, staff and community members are our top priority when planning school repairs. Our Facility Services staff works year-round to ensure our schools are safe regardless of their FCI rating.

Almost half of TDSB school buildings were built more than 60 years ago. Older schools often have a higher FCI rating as some building components such as walls, lights, floors and ventilation systems may require major repairs or replacement.


F.C.I.
47.02 %

Learn More

Learn more about the Renewal Needs Backlog and the Facility Condition Index, both of which include related Frequently Asked Questions.

Renewal Needs Backlog

The Toronto District School Board’s Renewal Needs Backlog (RNB) list identifies approximately 20,400 different repairs needed in our schools. The total value of those repairs was $4.2 billion as of March 2023.

For the 2022-2023 school year, the TDSB  received $292 million in provincial funding. These funds will be used to replace/repair building components identified during the Ministry’s school inspections, helping reduce the FCI of school buildings.

It is important to understand that these repairs do not represent a health or safety concern. Safety is a top priority for us at the TDSB and our maintenance plans are always focused on providing safe places for our students and staff. In order to do that, we fix the most critical problems related to health and safety first. Also, while components in a school building may be past their life expectancy (e.g. water boiler), they are in good condition and meet all required safety codes.

Legend

Urgent Building systems that are in critical condition and have surpassed their useful service life. These systems are very important to the operation of the building (e.g. boilers, other heat generating systems, fire alarm, sprinkler system, standpipe system, public address system, roofing, etc.). Although there is no specific timeframe to repair/replace these systems, it is recommended to do it as soon as funding becomes available.
High Building systems that are in critical or poor condition and their importance to the operation of the building is less than those classified as “urgent” (e.g. brick work, exterior doors, exterior windows, rooftop units, etc.). There is no specific timeframe to repair/replace these systems; however, repair/replacement is recommended as soon as funding becomes available.
Medium Building systems that are in fair condition with low importance to the operation of the building (e.g. floor finishes, washroom partitions, millwork, etc.).
Low Building systems that are in fair or good condition with very low importance to the operation of the building (e.g. wall partitions, interior wall finishes, interior doors, fences, etc.).
Brief DescriptionPriority
Auxiliary Equipment - Stacks & Breaching - Boiler #1 and #2 RenewalUrgent
Hot Water Boilers - Boiler #1 and #2 RenewalUrgent
Roof Coverings - Section B,D,D1,D2,D3,E RenewalUrgent
Auxiliary Equipment - Expansion Tanks - Boiler #1 and #2 RenewalHigh
B201011 Exterior Walls - Joint Sealant RenewalHigh
C1030 - Fittings - Washroom - Older RenewalHigh
Cooling Generating Systems - DX Split - CU #1 RenewalHigh
Distribution Systems - Air Distribution, Heating & Cooling - Duct System - 1978 RenewalHigh
Elevators and Lifts - Wheelchair Lift RenewalHigh
Exhaust Systems - Centrifugal Exhaust Fans - 1978 RenewalHigh
Exterior Doors RenewalHigh
Exterior Walls - Repairs RenewalHigh
Exterior Windows - 1978 Construction RenewalHigh
Fittings - Millwork RenewalHigh
Floor Finishes - Carpet RenewalHigh
Floor Finishes - Sheet vinyl RenewalHigh
G204010 Site Development - Exterior Stairs - Concrete Exterior Stairs RenewalHigh
Interior Stair Construction - 3 interior steel framed stairs RenewalHigh
Lighting and Branch Wiring - Exterior Lighting - Pole Mounted RenewalHigh
Parking Lots - Asphalt Paving RenewalHigh
Pedestrian Paving - Asphalt RenewalHigh
Playing Fields - Paved RenewalHigh
Playing Fields - Unpaved RenewalHigh
Rain Water Drainage RenewalHigh
Roadways - Original Building RenewalHigh
Roof Coverings - Section AB1,AB2,AB3,AD1,AD2,CD1,CD2 RenewalHigh
Standard Foundations - Repairs RenewalHigh
Terminal and Package Units - Unit Ventilators RenewalHigh
Wall Finishes - Painted RenewalHigh
Auxiliary Equipment - HVAC Pumps RenewalMedium
C302004 Floor Finishes - Vinyl Tile RenewalMedium
Ceiling Finishes - Original Building RenewalMedium
Exterior Doors - Hardware RenewalMedium
Floor Finishes - Hardwood RenewalMedium
Interior Doors - 1978 Construction RenewalMedium
Interior Doors - Hardware - 1978 Construction RenewalMedium
Landscaping RenewalMedium
Air Handling Units - SF #1 and #2 RenewalLow
Auxiliary Equipment - Chemical Feed Systems RenewalLow
Ceiling Finishes - Suspended ceiling panels RenewalLow
Domestic Water Distribution - Drinking Fountains and Coolers RenewalLow
Domestic Water Distribution - Pipes and Fittings RenewalLow
Fencing & Gates - Chain Link Fence RenewalLow
Fittings - Metal - 1998 Construction RenewalLow
Fittings - Window Coverings RenewalLow
Signage RenewalLow