Facility Condition Index

2022 -2023

The Facility Condition Index (FCI) rating is a measurement of the condition of a school building. It does not reflect on the safety of the building.

The health and safety of students, staff and community members are our top priority when planning school repairs. Our Facility Services staff works year-round to ensure our schools are safe regardless of their FCI rating.

Almost half of TDSB school buildings were built more than 60 years ago. Older schools often have a higher FCI rating as some building components such as walls, lights, floors and ventilation systems may require major repairs or replacement.


F.C.I.
96.28 %

Learn More

Learn more about the Renewal Needs Backlog and the Facility Condition Index, both of which include related Frequently Asked Questions.

Renewal Needs Backlog

The Toronto District School Board’s Renewal Needs Backlog (RNB) list identifies approximately 20,400 different repairs needed in our schools. The total value of those repairs was $4.2 billion as of March 2023.

For the 2022-2023 school year, the TDSB  received $292 million in provincial funding. These funds will be used to replace/repair building components identified during the Ministry’s school inspections, helping reduce the FCI of school buildings.

It is important to understand that these repairs do not represent a health or safety concern. Safety is a top priority for us at the TDSB and our maintenance plans are always focused on providing safe places for our students and staff. In order to do that, we fix the most critical problems related to health and safety first. Also, while components in a school building may be past their life expectancy (e.g. water boiler), they are in good condition and meet all required safety codes.

Legend

Urgent Building systems that are in critical condition and have surpassed their useful service life. These systems are very important to the operation of the building (e.g. boilers, other heat generating systems, fire alarm, sprinkler system, standpipe system, public address system, roofing, etc.). Although there is no specific timeframe to repair/replace these systems, it is recommended to do it as soon as funding becomes available.
High Building systems that are in critical or poor condition and their importance to the operation of the building is less than those classified as “urgent” (e.g. brick work, exterior doors, exterior windows, rooftop units, etc.). There is no specific timeframe to repair/replace these systems; however, repair/replacement is recommended as soon as funding becomes available.
Medium Building systems that are in fair condition with low importance to the operation of the building (e.g. floor finishes, washroom partitions, millwork, etc.).
Low Building systems that are in fair or good condition with very low importance to the operation of the building (e.g. wall partitions, interior wall finishes, interior doors, fences, etc.).
Brief DescriptionPriority
A101004 Standard Foundations Repairs - Damp proofing Repairs RenewalUrgent
A101004 Standard Foundations Repairs - Parging repairs RenewalUrgent
Auxiliary Equipment - Expansion Tanks RenewalUrgent
Auxiliary Equipment - HVAC Pumps RenewalUrgent
Auxiliary Equipment - Heat Exchanger - Shell & Tube - DHW RenewalUrgent
Auxiliary Equipment - Stacks & Breaching RenewalUrgent
Distribution Systems - Heated Water Distribution Systems - Piping System RenewalUrgent
G30 - Underground Utilities RenewalUrgent
Hot Water Boilers - Boilers #1, #2 and #3 RenewalUrgent
Roof Coverings - Section A1,A2,A3,A4,B4,B5,B7,E RenewalUrgent
Secondary Transformers RenewalUrgent
Air Distribution, Heating & Cooling - Duct System RenewalHigh
Air Handling Units - Central Station AHU's RenewalHigh
Auxiliary Equipment - Chemical Feed System RenewalHigh
B201014 Exterior Walls - Masonry Re-pointing RenewalHigh
B203004 Exterior Doors - Overhead RenewalHigh
B203008 Exterior Doors - Hardware RenewalHigh
Branch Wiring - Cabling, Raceway and Bus Ducts RenewalHigh
Brick Cavity Walls - CMU Backup - Localized Deficiencies RenewalHigh
C102007 Interior Doors - Hardware RenewalHigh
C103005 Fittings - Lockers RenewalHigh
C103009 Fittings - Millwork - Classrooms RenewalHigh
C103010 Fittings - Millwork - Laboratories - Older RenewalHigh
C103017 Fittings - Auditorium Seating RenewalHigh
C302002 Floor Finishes - Terrazzo - Localized Deficiencies RenewalHigh
C302004 Floor Finishes - Vinyl Tile - Older RenewalHigh
C302007 Floor Finishes - Painted Sealed Concrete RenewalHigh
C303004 Ceiling Finishes - Acoustic - Older RenewalHigh
Controls and Instrumentation - Pneumatic RenewalHigh
Cooling Generating Systems - DX Split - Condensers RenewalHigh
Domestic Water Distribution - Domestic Hot Water Storage Tank RenewalHigh
Domestic Water Distribution - Plumbing Piping System RenewalHigh
Elevators and Lifts - Passenger - Hydraulic RenewalHigh
Energy Supply System - Natural Gas - Piping RenewalHigh
Exhaust Systems - Centrifugal RenewalHigh
Exterior Doors - 65% RenewalHigh
Exterior Windows - All RenewalHigh
Exterior Windows - Sloped Glazing RenewalHigh
Floor Finishes - Carpet RenewalHigh
Floor Finishes - Hardwood RenewalHigh
Floor Finishes - Sheet Vinyl RenewalHigh
G202003 Parking Lots & Roadways - Paved - Asphalt RenewalHigh
G204001 Fencing and Gates - Chain Link Fence RenewalHigh
G204072 Playing Fields - Running Track RenewalHigh
Interior Doors - RenewalHigh
Lighting and Branch Wiring - Exterior Lighting RenewalHigh
Lighting and Branch Wiring - Interior Lighting RenewalHigh
Pedestrian Paving - All RenewalHigh
Perimeter Heating - Terminal Units RenewalHigh
Plumbing Fixtures - Bradley Basins RenewalHigh
Plumbing Fixtures - Lavatories RenewalHigh
Plumbing Fixtures - Urinals RenewalHigh
Plumbing Fixtures - Water Closets RenewalHigh
Plumbing Fixtures - Water Coolers RenewalHigh
Roof Top AHU - Heat & Cool - Carrier RenewalHigh
Wall Finishes - Painted RenewalHigh
C1010 Partitions - Localized Deficiencies RenewalMedium
C101003 Partitions - Moveable - Foldable Partition (Classroom) - Staffroom RenewalMedium
C101003 Partitions - Moveable - Foldable Partition (GYM) & Auditorium RenewalMedium
C103001 Fittings - Washroom Partitions - Water Closet RenewalMedium
C103002 Fittings - Washroom Accessories RenewalMedium
Exterior Walls - Control Joints RenewalMedium
Floor Finishes - Ceramic Tiles RenewalMedium
Interior Stair Construction RenewalMedium
Roof Coverings - Section B1 RenewalMedium
Wall Finishes - Ceramic Tiles RenewalMedium
Other Special Systems and Devices - Dust Collector RenewalLow
Playing Fields - Site Development RenewalLow
Stormwater Management - Site Storm System RenewalLow
Wall Finishes - Acoustical Wall Panels RenewalLow