Facility Condition Index

2022 -2023

The Facility Condition Index (FCI) rating is a measurement of the condition of a school building. It does not reflect on the safety of the building.

The health and safety of students, staff and community members are our top priority when planning school repairs. Our Facility Services staff works year-round to ensure our schools are safe regardless of their FCI rating.

Almost half of TDSB school buildings were built more than 60 years ago. Older schools often have a higher FCI rating as some building components such as walls, lights, floors and ventilation systems may require major repairs or replacement.


F.C.I.
71.56 %

Learn More

Learn more about the Renewal Needs Backlog and the Facility Condition Index, both of which include related Frequently Asked Questions.

Renewal Needs Backlog

The Toronto District School Board’s Renewal Needs Backlog (RNB) list identifies approximately 20,400 different repairs needed in our schools. The total value of those repairs was $4.2 billion as of March 2023.

For the 2022-2023 school year, the TDSB  received $292 million in provincial funding. These funds will be used to replace/repair building components identified during the Ministry’s school inspections, helping reduce the FCI of school buildings.

It is important to understand that these repairs do not represent a health or safety concern. Safety is a top priority for us at the TDSB and our maintenance plans are always focused on providing safe places for our students and staff. In order to do that, we fix the most critical problems related to health and safety first. Also, while components in a school building may be past their life expectancy (e.g. water boiler), they are in good condition and meet all required safety codes.

Legend

Urgent Building systems that are in critical condition and have surpassed their useful service life. These systems are very important to the operation of the building (e.g. boilers, other heat generating systems, fire alarm, sprinkler system, standpipe system, public address system, roofing, etc.). Although there is no specific timeframe to repair/replace these systems, it is recommended to do it as soon as funding becomes available.
High Building systems that are in critical or poor condition and their importance to the operation of the building is less than those classified as “urgent” (e.g. brick work, exterior doors, exterior windows, rooftop units, etc.). There is no specific timeframe to repair/replace these systems; however, repair/replacement is recommended as soon as funding becomes available.
Medium Building systems that are in fair condition with low importance to the operation of the building (e.g. floor finishes, washroom partitions, millwork, etc.).
Low Building systems that are in fair or good condition with very low importance to the operation of the building (e.g. wall partitions, interior wall finishes, interior doors, fences, etc.).
Brief DescriptionPriority
Auxiliary Equipment - Expansion Tank RenewalUrgent
Auxiliary Equipment - HVAC Pumps RenewalUrgent
Auxiliary Equipment - Stacks & Breaching RenewalUrgent
Hot Water Boilers - Boilers #1 and #2 RenewalUrgent
C1030 - Fittings - Washroom RenewalHigh
C103009 Fittings - Millwork - Laboratories RenewalHigh
C302004 Floor Finishes - Vinyl Tile RenewalHigh
Ceiling Finishes - Gypsum Board Ceiling RenewalHigh
Controls and Instrumentation - BAS RenewalHigh
Controls and Instrumentation - Pneumatic RenewalHigh
Distribution Systems - Exhaust Systems - Axial RenewalHigh
Domestic Water Distribution - Drinking Fountains and Coolers RenewalHigh
Electrical Service and Distribution - Panelboards RenewalHigh
Energy Supply System - Natural Gas RenewalHigh
Exterior Doors - Hardware RenewalHigh
Exterior Doors - Painted Hollow Metal Doors RenewalHigh
Exterior Windows - Bay RenewalHigh
Fencing & Gates - Perimeter Chain Link Fencing RenewalHigh
Fin Tube Radiation Units - Forced Flow Heaters RenewalHigh
Fittings - Millwork - Cabinetry, Shelves and Counters RenewalHigh
Interior Doors - Aged Door Hardware RenewalHigh
Interior Doors - Aged RenewalHigh
Interior Stair Construction - Steel Framed Stairs RenewalHigh
Lighting and Branch Wiring - Exterior Lighting - Wall Mounted RenewalHigh
Main Switchboards - Secondary Switchgear RenewalHigh
Other Special Systems and Devices - Dust Collector RenewalHigh
Parking Lots - Asphalt Paved Parking Area RenewalHigh
Pedestrian Paving - Asphalt and Concrete Paved RenewalHigh
Playing Fields - Asphalt Paved Play Areas RenewalHigh
Playing Fields - Baseball Diamond and Soccer Field - Unpaved RenewalHigh
Plumbing Fixtures - Bradley Basins RenewalHigh
Rain Water Drainage RenewalHigh
Sanitary Waste RenewalHigh
Site Development - Exterior Stairs RenewalHigh
Ceiling Finishes - Suspended Acoustic Ceiling Tiles RenewalMedium
Distribution Systems - Exhaust Systems - Centrifugal RenewalMedium
Domestic Water Distribution - Natural Gas DWH RenewalMedium
Domestic Water Distribution - Pipes and Fittings RenewalMedium
Fittings - Lockers RenewalMedium
Floor Finishes - Hardwood - Gym [Wood Parquet] RenewalMedium
Heating Water Distribution Systems - Heating Piping RenewalMedium
Partitions - Deteriorated RenewalMedium
Wall Finishes - Painted - Classroom Walls RenewalMedium
Fittings - Blinds and Shades RenewalLow
Fittings - Chalkboards RenewalLow
Landscaping - Site Landscaping RenewalLow
Lighting and Branch Wiring - Branch Wiring - Cabling, Raceways & Bus Ducts Low Density RenewalLow
Pedestrian Paving - Barrier Gate RenewalLow
Plumbing Fixtures - Lavatories RenewalLow
Plumbing Fixtures - Urinals RenewalLow
Signage - Printed Wall Mounted Sign RenewalLow
Stormwater Management RenewalLow
Wall Finishes - Vinyl Wallcovering - Second Floor RenewalLow