Brief Description | Priority |
Auxiliary Equipment - Expansion Tanks Renewal | Urgent |
Auxiliary Equipment - Stacks & Breaching Renewal | Urgent |
Hot Water Boilers - Boilers #1 and #2 Renewal | Urgent |
Air Handling Units - SF #1, #2 and #3 Renewal | High |
B201011 Exterior Walls - Joint Sealant Renewal | High |
C102007 Interior Doors - Hardware Renewal | High |
C2020 Stair Finishes - Anti-skid tape Renewal | High |
C302004 Floor Finishes - Vinyl Tile Renewal | High |
Ceiling Finishes - Acoustic Tiles - 1963 construction Renewal | High |
Controls and Instrumentation - Pneumatic Renewal | High |
Cooling Generating Systems - Window AC Renewal | High |
Domestic Water Distribution - Drinking Fountains and Coolers Renewal | High |
Electrical Service and Distribution - Panelboards Renewal | High |
Energy Supply System - Natural Gas Renewal | High |
Exhaust Systems - Centrifugal Renewal | High |
Exterior Doors - Hardware Renewal | High |
Exterior Doors Renewal | High |
Exterior Windows - Single glazed windows Renewal | High |
Fin Tube Radiation Units - Perimeter Heating Renewal | High |
Floor Finishes - Hardwood Renewal | High |
Floor Finishes - Library Carpet Renewal | High |
G204002 Retaining Walls - Rail Ties Renewal | High |
G204010 Site Development - Exterior Stairs - Concrete Exterior Stairs Renewal | High |
Interior Doors - Wooden Classroom & Metal Hallway Doors Renewal | High |
Lighting and Branch Wiring - Exterior Lighting - Wall Mounted Renewal | High |
Main Switchboards - Switchgear Renewal | High |
Parking Lots - Asphalt - North & West Renewal | High |
Pedestrian Paving - Concrete and asphalt walkways Renewal | High |
Playing Fields - Asphalt Playground Renewal | High |
Playing Fields - Unpaved - One Soccer & One Baseball Diamond Renewal | High |
Plumbing Fixtures - Bradley Basins Renewal | High |
Plumbing Fixtures - Lavatories Renewal | High |
Plumbing Fixtures - Water Closets Renewal | High |
Roadways - Paved Roadway Renewal | High |
Sanitary Waste Renewal | High |
B308020 Exterior Soffits Renewal | Medium |
C1010 Partitions - Localized Deficiencies Renewal | Medium |
C1030 - Fittings - Washroom Renewal | Medium |
Ceiling Finishes - Acoustic Tile 2'X4' - Suspended Tiles Renewal | Medium |
Domestic Water Distribution - Pipes and Fittings Renewal | Medium |
Fittings - Millwork Renewal | Medium |
Floor Finishes - Ceramic Tile Renewal | Medium |
Heating Water Distribution Systems - Pipes and Fittings Renewal | Medium |
Interior Stair Construction - Four stairs in 1963 & 1971 constructions Renewal | Medium |
Lighting and Branch Wiring - Branch Wiring - Cabling, Raceways & Bus Ducts Low Density Renewal | Medium |
Wall Finishes - Ceramic Tile Renewal | Medium |
Wall Finishes - Painted - 1963 & 1971 constructions Renewal | Medium |
Controls and Instrumentation - BAS Renewal | Low |
Domestic Water Distribution - DHWH #1 and #2 Renewal | Low |
Fittings - One retractable stage in 1963 construction Renewal | Low |
Landscaping - Decorative trees Renewal | Low |
Pedestrian Paving - Two chain and post arrangements Renewal | Low |
Rain Water Drainage Renewal | Low |
Signage - One wall mounted sign Renewal | Low |
Stormwater Management Renewal | Low |